Construction Updates

Residential Construction Updates: Cougar Village II and Cougar Place Replacement
Cougar Place Replacement Camera 1
Cougar Place Replacement Camera 2
Please check back every week for more construction updates.
Posted September 26, 2012
Cougar Place
Building B (south building)
- Window installation 95% in courtyard; 85% rest of building B
- Application of liquid waterproofing in process in courtyard
- Gypsum sheathing 95%
- Roof deck complete; Roofing installation starts
- Brick delivery scheduled
- Mockup is framed and sheathed and ready for brick
- Window testing scheduled for Oct. 4 and/or 5
- First floor corridor piping complete
- Fire Sprinkler rough in complete through third floor
- Electrical wall rough and plumbing rough in complete in units
- Chilled water risers complete
- Building B stair installation in process
Building C (north building)
- Framing 100%; Northside roof deck in process; Southside roof trusses being erected
- Sheathing 50% complete
- Window installation to start
- Electrical rough in and plumbing rough in through third floor
- First floor corridor pipe rough in ongoing
- Pre-rock of first floor corridor complete
Building A (commons and classroom building)
- Structural steel on site; Erection to start
Site work
- Electrical duct banks being finished to permanent power pole
- Fence relocated for playground expansion
1A Parking Garage
- Spread footing installation will occur through mid-October
- Shear walls and plinths are being added as footings are installed
- Storm sewer installation has started and will proceed thru early October
- Structural backfill was set to start this week
Two-week look ahead
- Structural excavation
- Spread footing installation
- Storm sewer installation
Cougar Village II
Last week’s accomplishments
- Framed/poured walls/columns on level 2 Area C
- Framed/poured grade beams in Area B
- Installed 3.5 bays of tunnel form framing
Two-week look ahead
- Grade beam completion in Area A
- Complete backfill in Area A
- Complete structural slab-on-grade pour Area A/B
- Level 3/4 Area C tunnel forms
Challenges
- Miscellaneous tunnel form materials delivery from Turkey
Posted: September 18, 2012
Cougar Village II
- Framed/Poured remaining walls/columns on Level 1 Area C
- Framed/Poured Level 2 Area C Flat Plate
- Completed U/G Plumbing & Electrical Rough-in Area B
- Installed 250′ of Storm Sewer Line along West Side of Site
Two-week look ahead
- Grade beam completion in Area B/A
- Complete Backfill in Area B/A
- Structural Slab-on-Grade Pour Area B
- Westside Utility Installation
- Level 3 Tunnel Forms
Cougar Place
- Wood decking installation will be complete this week and roofing installation begins next week at building B.
- Vinyl windows and exterior sheathing installation continues.
- Stairs will be installed this week.
- Next week brick will be delivered to the site.
- Steel will be delivered to the site this week for framing of the commons area in building A.
1A Parking Garage
- Spread footing installation will occur thru mid October.
- Shear walls and plinths are being added as footings are installed.
- Structural backfill is scheduled to begin Sept. 24.
Two-week look ahead
- Structural excavation
- Spread footing installation
Posted: September 11, 2012
Cougar Village II
- Framed/Poured Level 1 Columns and Walls Area C
- Began scaffolding/decking for Level 2 Area C Flat Plate Pour
- Completed U/G Plumbing & Electrical Rough-in Area A/B
- Completed Structural Slab-on-Grade Area C
- Installed 300′ of Storm Sewer Line along West Side of Site
Two-week look ahead
- Grade beam completion in Area B/A
- Complete Backfill in Area B/A
- Structural Slab-on-Grade Pour Area B
- Westside Utility Installation
- Level 2 Elevated Deck – Flat Plate Pour Area B
Cougar Place
Building B (South Building)
- Roof sheathing
- Dens Glass Sheathing installation at exterior
- Structural Steel Erection on south side complete; Crane moved to north side
- Third Floor Framing infill over Mechanical Room
- Electrical rough-in in walls is ongoing through the 4th floor
- Fire Sprinkler installation in progress
- Vinyl Window installation in progress
- Waterproofing for Vinyl Windows in progress
Building C (North Building)
- Floor Trusses 3rd floor on South side in progress
- Roof Truss installation on North side
- Dens Glass being installed
- Structural Steel Erection in progress in C.
- Plumbing Rough In of second floor in progress
- Mechanical Layout and hanger installation
- Electrical rough-in in progress on 2nd Floor North Side
Building A (Commons & Classroom Building)
- Structural Steel delivery week of Sept. 18
Site Work
- Begin Layout for exterior system mock up.
1A Parking Garage
- Spread footings (7) were installed on the east side of the project.
- Spread footing installation will be installed continuously at the rate of 3 per day thru mid October.
Two-week look ahead
- Structural Excavation
- Spread Footing Installation
Posted: September 5, 2012
Cougar Village II
- Framed/Poured 200′ of Grade Beams in Area B
- Framed/Poured Exterior Columns at Breezeway and Area C
- U/G Plumbing & Electrical Rough-in Area A/B
- Poured Structural Slab-on-Grade Area C
Two-week look ahead
- Grade beam completion in Area B/A
- Complete Backfill in Area B/A
- Underground MEP work in Area B/A
- Structural Slab-on-Grade Pour Area B
- Westside Utility Installation
- Level 2 Elevated Deck – Flat Plate Pour Area C
Cougar Place
Building B (South Building)
- Roof Trusses being installed
- Dens Glass Sheathing installed in courtyard
- Structural Steel Erection on south side complete; Crane moved to north side
- Third Floor Framing infill over Mechanical Room in process
- Electrical rough-in in walls is ongoing through the 3rd floor
- Fire Sprinkler Shop Drawings Approved. Installation to start.
- Plumbing rough-in complete
- Water tank is installed.
- Vinyl Windows onsite
- Waterproofing for Vinyl Window to start
Building C (North Building)
- Framing 4th floor on north side begins
- Roof Truss installation on north side
- Dense Glass being installed.
- CMU work is Complete
- Structural Steel Erection in started in C.
- Plumbing Rough In Started
- Electrical rough-in started
Building A (Commons & Classroom Building)
- CMU walls complete
- Structural Steel delivery week of Sept. 7
Site Work
- Power Poles installed by CenterPoint Energy for permanent power
- Additional Trees removed
- Fence along Wheeler relocated for METRO access
1A Parking Garage
- Materials needed for footing installation have been delivered.
- Spread footing installation is scheduled to begin on east side of project.
Two-week look ahead
- Structural Excavation
- Spread Footing Installation
Posted August 22, 2012
1A Parking Garage
- Asphalt has been demolished and removed in areas to receive spread footings.
- Structural excavation and spread footing installation to begin next week.
- Two-week look ahead: Structural excavation and spread footing installation
Cougar Place
- Demolition phase is complete
- Bidding is complete, with the Best Value Package for Pkg. 4 under review and the buy-out report complete through Pkg. 3
- Substantial Completion of construction by June 13, 2013
- Road through the site from Cougar Place Drive to Cullen is complete! (milestone)
- Circle Drive off Cougar Place Drive to pour on Aug. 21
- Power Poles to be installed by CenterPoint Energy for permanent power
- Domestic Water Line Installed
- Fence along Wheeler to be relocated by Aug. 17
- Wood Storage on Parking Lot 11A to be removed by start of school
Building B: (South Building):
- Roof Trusses are being installed on 4th floor
- Dens Glass Sheathing is being installed
- Steel is being erected at study lounge area
- Stairs for Building B onsite
- Second Floor Concrete Slab to be poured over Mechanical Room on Aug. 21
- Electrical & Plumbing rough-in continues on Second Floor
- Electrical Rough In continues on Second Floor
- Mechanical, Plumbing, & Fire Sprinkler hangers installed in corridors
Building C: (North Building):
- Framing 4th floor on north side
- Floor trusses are being installed on the third floor on Southside
- CMU work is Complete
- Structural Steel Erection to start in C the end of next week
- Mechanical Hangers for Chilled Water Installed on First Floor
Building A: (Commons & Classroom Building):
- CMU on going to be complete next week
- Structural Steel delivery week of Aug. 27
Cougar Village II
Last Week’s Accomplishments:
- Framed/Poured 20 Plinths – only 2 remain
- Framed/Poured 300′ of Grade Beams in Area C – Complete in Area C
- Framed/Poured 60′ of Tunnel Walls
- Framed/Poured 2 Exterior Columns at Breezeway
- Completed Backfill Area C
- Started U/G Plumbing & Electrical Rough-in Area B
- Started excavation of tunnel connection in Parking Lot 6B
- Storm Sewer installation to building at Area C
Two-week look ahead:
- Foundation Walls completion in Area A
- Grade beam installation in Area B/A
- Complete Backfill in Area B/A
- Underground MEP work in Area B/A
- Structural Slab-on-Grade Pour Area C/B
- CV 2 Tunnel Connection
Challenges:
- Student Move-in Aug. 23-26
- Received three inches of rain over the weekend
- Unexpected Electrical Ductbank conflicts at Utility Tunnel
Posted: August 2, 2012
Cougar Village II
For next two weeks:
- Spread footing installation in Area A/B
- Structural Wall and Plinth installation in Area A/B
- Backfill Area C to below Structural Slab-on-Grade
- Grade beam installation in Area C
- Storm Sewer installation on the West side of the project
- Underground MEP work in Area B/C
- Utility Tunnel Excavation and Install
Cougar Place
- Wood framing on 3rd floor of building B and 2nd floor of building C is in process
- Wood decking @ 2nd floor is complete
- Framing hardware installation in process @ 1st floor
- CMU walls at elevator shaft at building C is 90% complete
- Structural steel on site 1st week of August in building A
- Installation of Sanitary Sewer & Storm will continue as weather permits
- Hauling of earth from utility excavations will continue as weather permits
- Electrical duct bank section 2 of 3 has be pumped out and re-dug 3 times this week.
- Road construction begins July 30th. Date pushed back 14 days due to weather.
1A Parking Garage
- Construction fence up on Friday, July 27
- Construction trailer scheudled for August 1
Posted: July 17,2012
Cougar Village II
For next two weeks:
- Spread footing installation in Area A/B
- Structural wall and plinth installation in Area A/B
- Backfill Area C to below structural Slab-on-Grade
- Grade beam installation in Area C
- Tower Crane foundation and erection
- Storm Sewer installation on the west side of the project
- Underground MEP work in Area B/C
Cougar Place
- Installation of sanitary sewer & storm continues
- Hauling of earth from utility excavations continues
- Electrical duct bank section 2 of 3 must be redone as rain damaged trench and conduit floated out.
- Framing of walls on 3rd floor/Building B and 2nd floor/Building C continues. It is taking 2 weeks per floor to frame walls.
- Rain on Sunday will likely create some site work delays on underground utilities.
- Road construction begins July 16th (pending duct bank completion)