Construction Updates

Residential Construction Updates: Cougar Village II and Cougar Place Replacement

Cougar Place Replacement Camera 1

Cougar Place Replacement Camera 2

Cougar Village II Camera 1

Cougar Village II Camera 2

Please check back every week for more construction updates.

Posted September 26, 2012

Cougar Place

Building B (south building)

  • Window installation 95% in courtyard; 85% rest of building B
  • Application of liquid waterproofing in process in courtyard
  • Gypsum sheathing 95%
  • Roof deck complete; Roofing installation starts
  • Brick delivery scheduled
  • Mockup is framed and sheathed and ready for brick
  • Window testing scheduled for Oct. 4 and/or 5
  • First floor corridor piping complete
  • Fire Sprinkler rough in complete through third floor
  • Electrical wall rough and plumbing rough in complete in units
  • Chilled water risers complete
  • Building B stair installation in process

Building C (north building)

  • Framing 100%; Northside roof deck in process; Southside roof trusses being erected
  • Sheathing 50% complete
  • Window installation to start
  • Electrical rough in and plumbing rough in through third floor
  • First floor corridor pipe rough in ongoing
  • Pre-rock of first floor corridor complete

Building A (commons and classroom building)

  • Structural steel on site; Erection to start

Site work

  • Electrical duct banks being finished to permanent power pole
  • Fence relocated for playground expansion

1A Parking Garage

  • Spread footing installation will occur through mid-October
  • Shear walls and plinths are being added as footings are installed
  • Storm sewer installation has started and will proceed thru early October
  • Structural backfill was set to start this week

Two-week look ahead

  • Structural excavation
  • Spread footing installation
  • Storm sewer installation

Cougar Village II

Last week’s accomplishments

  • Framed/poured walls/columns on level 2 Area C
  • Framed/poured grade beams in Area B
  • Installed 3.5 bays of tunnel form framing

Two-week look ahead

  • Grade beam completion in Area A
  • Complete backfill in Area A
  • Complete structural slab-on-grade pour Area A/B
  • Level 3/4 Area C tunnel forms

Challenges

  • Miscellaneous tunnel form materials delivery from Turkey

Posted: September 18, 2012

Cougar Village II

  • Framed/Poured remaining walls/columns on Level 1 Area C
  • Framed/Poured Level 2 Area C Flat Plate
  • Completed U/G Plumbing & Electrical Rough-in Area B
  • Installed 250′ of Storm Sewer Line along West Side of Site

Two-week look ahead

  • Grade beam completion in Area B/A
  • Complete Backfill in Area B/A
  • Structural Slab-on-Grade Pour Area B
  • Westside Utility Installation
  • Level 3 Tunnel Forms

Cougar Place

  • Wood decking installation will be complete this week and roofing installation begins next week at building B.
  • Vinyl windows and exterior sheathing installation continues.
  • Stairs will be installed this week.
  • Next week brick will be delivered to the site.
  • Steel will be delivered to the site this week for framing of the commons area in building A.

1A Parking Garage

  • Spread footing installation will occur thru mid October.
  • Shear walls and plinths are being added as footings are installed.
  • Structural backfill is scheduled to begin Sept. 24.

Two-week look ahead

  • Structural excavation
  • Spread footing installation

Posted: September 11, 2012

Cougar Village II

  • Framed/Poured Level 1 Columns and Walls Area C
  • Began scaffolding/decking for Level 2 Area C Flat Plate Pour
  • Completed U/G Plumbing & Electrical Rough-in Area A/B
  • Completed Structural Slab-on-Grade Area C
  • Installed 300′ of Storm Sewer Line along West Side of Site

Two-week look ahead

  • Grade beam completion in Area B/A
  • Complete Backfill in Area B/A
  • Structural Slab-on-Grade Pour Area B
  • Westside Utility Installation
  • Level 2 Elevated Deck – Flat Plate Pour Area B

Cougar Place

Building B (South Building)

  • Roof sheathing
  • Dens Glass Sheathing installation at exterior
  • Structural Steel Erection on south side complete; Crane moved to north side
  • Third Floor Framing infill over Mechanical Room
  • Electrical rough-in in walls is ongoing through the 4th floor
  • Fire Sprinkler installation in progress
  • Vinyl Window installation in progress
  • Waterproofing for Vinyl Windows in progress

Building C (North Building)

  • Floor Trusses 3rd floor on South side in progress
  • Roof Truss installation on North side
  • Dens Glass being installed
  • Structural Steel Erection in progress in C.
  • Plumbing Rough In of second floor in progress
  • Mechanical Layout and hanger installation
  • Electrical rough-in in progress on 2nd Floor North Side

Building A (Commons & Classroom Building)

  • Structural Steel delivery week of Sept. 18

Site Work

  • Begin Layout for exterior system mock up.

1A Parking Garage

  • Spread footings (7) were installed on the east side of the project.
  • Spread footing installation will be installed continuously at the rate of 3 per day thru mid October.

Two-week look ahead

  • Structural Excavation
  • Spread Footing Installation

Posted: September 5, 2012

Cougar Village II

  • Framed/Poured 200′ of Grade Beams in Area B
  • Framed/Poured Exterior Columns at Breezeway and Area C
  • U/G Plumbing & Electrical Rough-in Area A/B
  • Poured Structural Slab-on-Grade Area C

Two-week look ahead

  • Grade beam completion in Area B/A
  • Complete Backfill in Area B/A
  • Underground MEP work in Area B/A
  • Structural Slab-on-Grade Pour Area B
  • Westside Utility Installation
  • Level 2 Elevated Deck – Flat Plate Pour Area C

Cougar Place

Building B (South Building)

  • Roof Trusses being installed
  • Dens Glass Sheathing installed in courtyard
  • Structural Steel Erection on south side complete; Crane moved to north side
  • Third Floor Framing infill over Mechanical Room in process
  • Electrical rough-in in walls is ongoing through the 3rd floor
  • Fire Sprinkler Shop Drawings Approved. Installation to start.
  • Plumbing rough-in complete
  • Water tank is installed.
  • Vinyl Windows onsite
  • Waterproofing for Vinyl Window to start

Building C (North Building)

  • Framing 4th floor on north side begins
  • Roof Truss installation on north side
  • Dense Glass being installed.
  • CMU work is Complete
  • Structural Steel Erection in started in C.
  • Plumbing Rough In Started
  • Electrical rough-in started

Building A (Commons & Classroom Building)

  • CMU walls complete
  • Structural Steel delivery week of Sept. 7

Site Work

  • Power Poles installed by CenterPoint Energy for permanent power
  • Additional Trees removed
  • Fence along Wheeler relocated for METRO access

1A Parking Garage

  • Materials needed for footing installation have been delivered.
  • Spread footing installation is scheduled to begin on east side of project.

Two-week look ahead

  • Structural Excavation
  • Spread Footing Installation

Posted August 22, 2012

1A Parking Garage

  • Asphalt has been demolished and removed in areas to receive spread footings.
  • Structural excavation and spread footing installation to begin next week.
  • Two-week look ahead: Structural excavation and spread footing installation

Cougar Place

  • Demolition phase is complete
  • Bidding is complete, with the Best Value Package for Pkg. 4 under review and the buy-out report complete through Pkg. 3
  • Substantial Completion of construction by June 13, 2013
  • Road through the site from Cougar Place Drive to Cullen is complete! (milestone)
  • Circle Drive off Cougar Place Drive to pour on Aug. 21
  • Power Poles to be installed by CenterPoint Energy for permanent power
  • Domestic Water Line Installed
  • Fence along Wheeler to be relocated by Aug. 17
  • Wood Storage on Parking Lot 11A to be removed by start of school

Building B: (South Building):

  • Roof Trusses are being installed on 4th floor
  • Dens Glass Sheathing is being installed
  • Steel is being erected at study lounge area
  • Stairs for Building B onsite
  • Second Floor Concrete Slab to be poured over Mechanical Room on Aug. 21
  • Electrical & Plumbing rough-in continues on Second Floor
  • Electrical Rough In continues on Second Floor
  • Mechanical, Plumbing, & Fire Sprinkler hangers installed in corridors

Building C: (North Building):

  • Framing 4th floor on north side
  • Floor trusses are being installed on the third floor on Southside
  • CMU work is Complete
  • Structural Steel Erection to start in C the end of next week
  • Mechanical Hangers for Chilled Water Installed on First Floor

Building A: (Commons & Classroom Building):

  • CMU on going to be complete next week
  • Structural Steel delivery week of Aug. 27

Cougar Village II

Last Week’s Accomplishments:

  • Framed/Poured 20 Plinths – only 2 remain
  • Framed/Poured 300′ of Grade Beams in Area C – Complete in Area C
  • Framed/Poured 60′ of Tunnel Walls
  • Framed/Poured 2 Exterior Columns at Breezeway
  • Completed Backfill Area C
  • Started U/G Plumbing & Electrical Rough-in Area B
  • Started excavation of tunnel connection in Parking Lot 6B
  • Storm Sewer installation to building at Area C

Two-week look ahead:

  • Foundation Walls completion in Area A
  • Grade beam installation in Area B/A
  • Complete Backfill in Area B/A
  • Underground MEP work in Area B/A
  • Structural Slab-on-Grade Pour Area C/B
  • CV 2 Tunnel Connection

Challenges:

  • Student Move-in Aug. 23-26
  • Received three inches of rain over the weekend
  • Unexpected Electrical Ductbank conflicts at Utility Tunnel

Posted: August 2, 2012

Cougar Village II

For next two weeks:

  • Spread footing installation in Area A/B
  • Structural Wall and Plinth installation in Area A/B
  • Backfill Area C to below Structural Slab-on-Grade
  • Grade beam installation in Area C
  • Storm Sewer installation on the West side of the project
  • Underground MEP work in Area B/C
  • Utility Tunnel Excavation and Install

Cougar Place

  • Wood framing on 3rd floor of building B and 2nd floor of building C is in process
  • Wood decking @ 2nd floor is complete
  • Framing hardware installation in process @ 1st floor
  • CMU walls at elevator shaft at building C is 90% complete
  • Structural steel on site 1st week of August in building A
  • Installation of Sanitary Sewer & Storm will continue as weather permits
  • Hauling of earth from utility excavations will continue as weather permits
  • Electrical duct bank section 2 of 3 has be pumped out and re-dug 3 times this week.
  • Road construction begins July 30th. Date pushed back 14 days due to weather.

1A Parking Garage

  • Construction fence up on Friday, July 27
  • Construction trailer scheudled for August 1

Posted: July 17,2012

Cougar Village II
For next two weeks:

  • Spread footing installation in Area A/B
  • Structural wall and plinth installation in Area A/B
  • Backfill Area C to below structural Slab-on-Grade
  • Grade beam installation in Area C
  • Tower Crane foundation and erection
  • Storm Sewer installation on the west side of the project
  • Underground MEP work in Area B/C

Cougar Place

  • Installation of sanitary sewer & storm continues
  • Hauling of earth from utility excavations continues
  • Electrical duct bank section 2 of 3 must be redone as rain damaged trench and conduit floated out.
  • Framing of walls on 3rd floor/Building B and 2nd floor/Building C continues. It is taking 2 weeks per floor to frame walls.
  • Rain on Sunday will likely create some site work delays on underground utilities.
  • Road construction begins July 16th (pending duct bank completion)